Application NumberTitleFiling DateDisposal DateDispositionTime (months)Office ActionsRestrictionsInterviewAppeal
19283375TURBINE ENCLOSURE VENTILATION AIR DUCTING FOR AIR HANDLING TRANSPORTJuly 2025December 2025Allow510NoNo
19228829EMISSIONS OF NON-VOLATILE PARTICULATE MATTER FROM GAS TURBINE ENGINES COMBUSTING SUSTAINABLE AVIATION FUEL AND FOSSIL-BASED HYDROCARBON FUELJune 2025February 2026Allow910NoNo
19049033CYCLONIC SEPARATOR FOR GAS TURBINE ENGINEFebruary 2025March 2026Allow1310NoNo
19047035COMBUSTOR LINER PANELSFebruary 2025September 2025Allow710NoNo
19047165AIRCRAFT AIR SYSTEM WITH ELECTRIC BOOST COMPRESSORFebruary 2025October 2025Allow810NoNo
19042124GAS TURBINE ENGINE WITH THIRD STREAMJanuary 2025January 2026Allow1210NoNo
19043121GAS TURBINE ENGINEJanuary 2025November 2025Allow900NoNo
19018995ACCESSIBLE DEBRIS SEPARATOR FOR HIGH PRESSURE TURBINE OUTSIDE DIAMETER FED STATIC COMPONENTSJanuary 2025March 2026Allow1411NoNo
19016281GAS TURBINE ENGINE WITH THIRD STREAMJanuary 2025September 2025Allow800NoNo
19017029GAS TURBINE ENGINE HAVING A BYPASS PASSAGE, A FAN DUCT, AND A CORE DUCTJanuary 2025December 2025Allow1110NoNo
18991142GAS TURBINE ENGINE WITH THIRD STREAMDecember 2024November 2025Allow1010NoNo
18982445GAS TURBINE ENGINE WITH THIRD STREAMDecember 2024October 2025Allow1010NoNo
18962582BOSS FOR A FUEL INJECTION ASSEMBLY HAVING COOLING CIRCUIT AND COMBUSTOR PROVIDED THEREWITHNovember 2024August 2025Allow910NoNo
18962602MULTISTAGE VARIABLE BURNING RATE SOLID ROCKET MOTOR AND FORMING METHODNovember 2024July 2025Allow820NoNo
18960450AIRCRAFT POWERPLANT GEARBOX WITH SELECTABLE POWER COUPLERNovember 2024September 2025Allow910NoNo
18960990ROCKET MOTOR INCLUDING AN EMBEDDED CHARGE ASSEMBLY (ECA) CONFIGURED TO SUPPORT A BURN RATE ENHANCEMENT (BRE) WIRENovember 2024July 2025Allow710YesNo
18960971CONTROLLING SUPPLY OF AIRCRAFT ENGINE WITH MULTIPLE FUELSNovember 2024September 2025Allow1010NoNo
18949096COMBUSTOR HAVING A MAIN CHAMBER AND ONE OR MORE TRAPPED VORTEX CAVITIESNovember 2024August 2025Allow910YesNo
18945305ICE SLURRY FIREFIGHTING SYSTEMNovember 2024January 2026Allow1410YesNo
18942928ICE REDUCTION MECHANISM FOR TURBOFAN ENGINENovember 2024July 2025Allow810YesNo
18910948TURBINE ENGINE HAVING A VARIABLE ENGINE INTAKE SYSTEMOctober 2024June 2025Allow820YesNo
18910956TURBINE ENGINE HAVING A VARIABLE ENGINE INTAKE SYSTEMOctober 2024September 2025Allow1230YesNo
18892721GAS TURBINE PERFORMANCESeptember 2024September 2025Allow1121YesNo
18892666EMISSIONS OF NON-VOLATILE PARTICULATE MATTER FROM GAS TURBINE ENGINES COMBUSTING SUSTAINABLE AVIATION FUEL AND FOSSIL-BASED HYDROCARBON FUELSeptember 2024July 2025Allow1021YesNo
18883246POWERPLANT FOR AN AIRCRAFTSeptember 2024October 2025Allow1301NoNo
18827645ROTARY CLOSED-CYCLE EXTERNALLY-HEATED ENGINESeptember 2024September 2025Allow1211YesNo
18812564CHILLED INTAKE AIR FOR INCREASED POWER GENERATIONAugust 2024August 2025Allow1110NoNo
18807522COGENERATION OF CHEMICAL PRODUCTSAugust 2024August 2025Allow1210NoNo
18796846CONTROL SCHEMES FOR THERMAL MANAGEMENT OF POWER PRODUCTION SYSTEMS AND METHODSAugust 2024July 2025Allow1210NoNo
18788352AIR INTAKE WITH CHANGING WALL THICKNESS AND ASSOCIATED NACELLEJuly 2024December 2025Allow1630NoNo
18777047ROTATING DETONATION COMBUSTOR SYSTEM AND METHOD OF OPERATING THE ROTATING DETONATION COMBUSTOR SYSTEMJuly 2024November 2025Abandon1620NoNo
18770902Gas Turbine Engine with Third StreamJuly 2024August 2025Allow1311NoNo
18768665TURBINE ENGINE COMBUSTOR WITH A DILUTION PASSAGEJuly 2024May 2025Allow1110NoNo
18765270LIQUID SPRAY NOZZLE AND LIQUID SPRAY DEVICEJuly 2024March 2026Allow2021NoNo
18745648AIR COOLING SYSTEM FOR STATOR VANE STRUCTURE OUTER PLATFORMJune 2024July 2025Allow1310NoNo
18740613GAS TURBINE ENGINE WITH THIRD STREAMJune 2024November 2025Allow1721YesNo
18680469GAS TURBINE ENGINE WITH THIRD STREAMMay 2024November 2025Allow1711NoNo
18675270GAS TURBINE ENGINE WITH THIRD STREAMMay 2024September 2025Allow1611NoNo
18674441COMPRESSOR BLEED SLOTS WITH VARIABLE WALL STRUCTURESMay 2024July 2025Allow1411NoNo
18712415PRESSURIZATION OF A LUBRICATED TURBOMACHINE ENCLOSUREMay 2024August 2025Allow1520NoNo
18635564WATER SPRAY GUN HAVING SPRAY NOZZLE POSITIONING STRUCTUREApril 2024August 2025Allow1610NoNo
18628272TAILORING AIRCRAFT POWERPLANT SPLIT LINE PARAMETER WITH INFLATABLE BLADDERApril 2024August 2025Allow1730YesNo
18591389TURBINE ENGINE WITH INVERSE BRAYTON CYCLEFebruary 2024August 2025Allow1830NoNo
18428916SPLITTER FOR AERONAUTIC TURBOMACHINEJanuary 2024December 2025Allow2231YesNo
18417271SHOWER FOR A SANITARY FAUCETJanuary 2024March 2026Allow2520NoNo
18394029INJECTOR HEAD FOR FUEL INJECTORDecember 2023December 2025Allow2400NoNo
18389687SHOWER HEAD STRUCTURE AND SHOWER DEVICEDecember 2023January 2026Allow2510YesNo
18521325APPARATUSES AND METHODS FOR MEASURING FIRE SPREAD RATENovember 2023February 2026Allow2710NoNo
18464563DELIVERING FLUID THROUGH AN ELECTRIC VEHICLESeptember 2023November 2025Allow2710YesNo
18236275SYSTEMS AND METHODS FOR BATTERY THERMAL MANAGEMENT ON A VEHICLEAugust 2023December 2025Allow2810NoNo
18446496ENERGY STORAGE APPARATUS AND FIRE EXTINGUISHING METHOD THEREOFAugust 2023October 2025Allow2610YesNo
18214022SYSTEMS AND METHODS UTILIZING GAS TEMPERATURE AS A POWER SOURCEJune 2023September 2025Allow2741NoNo
18202731AIRCRAFT PROPULSION SYSTEM WITH VARIABLE SPEED ROTATING STRUCTUREMay 2023September 2025Allow2830NoNo
18110454GAS TURBINE ENGINE WITH HIGH SPEED LOW PRESSURE TURBINE SECTION AND BEARING SUPPORT FEATURESFebruary 2023September 2025Allow3120NoYes
18098920RADIAL STRUT FRAME CONNECTION BETWEEN FAN CASE AND CORE HOUSING IN A GAS TURBINE ENGINEJanuary 2023August 2025Allow3120NoYes
17896522FORCE MODIFICATION OF PASSIVE VALVE SPOOLS FOR CONTROL OF NOZZLESAugust 2022August 2025Allow3530NoNo
16384463HIGH EFFICIENCY POWER GENERATION SYSTEM AND SYSTEM UPGRADESApril 2019February 2021Allow2210NoNo
15953791INTEGRATED HEAT EXCHANGERS FOR LOW FAN PRESSURE RATIO GEARED TURBOFANApril 2018May 2020Allow2510NoNo
15725817SYSTEM AND METHOD FOR IMPINGEMENT COOLING OF TURBINE SYSTEM COMPONENTSOctober 2017April 2020Allow3110NoNo
15549050APPARATUS AND PROCESS OF RETROFITTING A COMBINED CYCLE POWER PLANTAugust 2017March 2020Allow3111NoNo
15620853ROCKET ENGINES SYSTEMSJune 2017April 2020Allow3420NoNo
15410946ENVIRONMENTAL CONTROL SYSTEM FOR AN AERONAUTIC VEHICLEJanuary 2017October 2019Allow3320YesNo
15389969GAS TURBINE COMBINED CYCLE FOR HIGH FLEXIBILITYDecember 2016June 2019Allow2910NoNo
15339630COOLED COMPONENT HAVING EFFUSION COOLING APERTURESOctober 2016May 2019Allow3011NoNo
15139970DEVICE FOR IMPROVED AIR AND FUEL DISTRIBUTION TO A COMBUSTORApril 2016January 2019Allow3220NoNo
15042586SURFACE CONTOURING OF A FLOWPATH WALL OF A GAS TURBINE ENGINEFebruary 2016July 2019Allow4141YesNo
14764375COWL WITH PRESSURE DRIVEN LATCHJuly 2015April 2016Allow900YesNo
14742760HIGH EFFICIENCY POWER GENERATION SYSTEM AND SYSTEM UPGRADESJune 2015March 2016Allow910NoNo
14741345REAGENT INJECTION SYSTEM FOR EXHAUST OF TURBINE SYSTEMJune 2015September 2015Allow310YesNo
14689265SYSTEMS AND METHODS FOR RESTRICTING MOVEMENT IN FLEXIBLE DUCTSApril 2015September 2019Allow5390YesNo
14638775GAS TURBINE DUCT CASINGMarch 2015March 2017Allow2510NoNo
14390783BURNER OF GAS TURBINE WITH FUEL NOZZLES TO INJECT FUELOctober 2014January 2017Allow2820NoNo
14501651GAS TURBINE WITH SEQUENTIAL COMBUSTION ARRANGEMENTSeptember 2014March 2017Allow2911YesNo
14499602METHOD AND DEVICE FOR SAFELY OPERATING A GAS TURBINE PLANTSeptember 2014November 2016Allow2510YesNo
14488652ANNULAR HELMHOLTZ DAMPERSeptember 2014December 2016Allow2710YesNo
14484684GAS EJECTION CONE FOR AIRCRAFT TURBOJET ENGINESSeptember 2014December 2016Allow2710YesNo
14377427Combined Cycle CAES Technology (CCC)August 2014February 2017Allow3020NoNo
14444253OPERATION OF GAS TURBINE POWER PLANT WITH CARBON DIOXIDE SEPARATIONJuly 2014March 2017Allow3220YesNo
14359155METHOD AND APPARATUS FOR SUPPLYING A COMBUSTION CHAMBER WITH NITROGENMay 2014December 2016Allow3120NoNo
14217106FUEL OXIDATION IN A GAS TURBINE SYSTEMMarch 2014October 2016Allow3110YesNo
14209749COMPACT ACTUATION SYSTEM FOR FLOW NOZZLEMarch 2014May 2016Allow2710YesNo
14148695COMBUSTION SYSTEMJanuary 2014February 2016Allow2510YesNo
14139209CARBON-FREE LOW-NOX LIQUID FUEL OXYGEN TRANSPORT REACTOR FOR INDUSTRIAL WATER TUBE BOILERSDecember 2013May 2016Allow2910YesNo
14135055SYSTEM AND METHOD FOR PROTECTING COMPONENTS IN A GAS TURBINE ENGINE WITH EXHAUST GAS RECIRCULATIONDecember 2013October 2016Allow3420YesNo
14105313SWIRLING MIDFRAME FLOW FOR GAS TURBINE ENGINE HAVING ADVANCED TRANSITIONSDecember 2013November 2016Allow3531NoNo
14105572MULTI-PASSAGE DIFFUSER WITH REACTIVATED BOUNDARY LAYERDecember 2013September 2016Allow3420YesNo
14122694COMBUSTOR AND METHOD OF SUPPLYING FUEL TO THE COMBUSTORNovember 2013April 2016Allow2920NoNo
13978948COMBUSTION CHAMBER WITH A WALL SECTION AND A BRIM ELEMENTOctober 2013December 2015Allow2910YesNo
14040972ANTI-FIRE SEAL ASSEMBLY AND NACELLE COMPRISING SUCH A SEALSeptember 2013September 2014Allow1120YesNo
14038016VARIABLE LENGTH COMBUSTOR DOME EXTENSION FOR IMPROVED OPERABILITYSeptember 2013January 2016Allow2810YesNo
13979782AVIATION GAS TURBINE THRUST REVERSING DEVICEAugust 2013March 2016Allow3220NoNo
13961257BORESCOPE ASSEMBLY AND METHOD OF INSTALLING BORESCOPE PLUGSAugust 2013July 2016Allow3520YesNo
13955107HEAT TRANSFER ASSEMBLY AND METHODS OF ASSEMBLING THE SAMEJuly 2013August 2016Allow3620NoNo
13941200COMPRESSED AIR ENERGY STORAGE SYSTEM HAVING VARIABLE GENERATION MODESJuly 2013February 2016Allow3220NoNo
13936424BURNER ARRANGEMENT INCLUDING AN AIR SUPPLY WITH TWO FLOW PASSAGESJuly 2013January 2017Allow4341YesNo
13905315Axial Compressor and Gas Turbine Having Axial CompressorMay 2013April 2016Allow3530NoNo
13712652GAS TURBINE WITH COULOMBIC THERMAL PROTECTIONDecember 2012October 2015Allow3420YesNo
13590172ROCKET ENGINE SYSTEMSAugust 2012February 2017Allow5441YesNo
13534744TRANSITION DUCT FOR A GAS TURBINEJune 2012August 2015Allow3710NoNo
13484410UTILIZATION OF FUEL GAS FOR PURGING A DORMANT FUEL GAS CIRCUITMay 2012June 2015Allow3710YesNo

Appeals Overview

This analysis examines appeal outcomes and the strategic value of filing appeals for examiner SUTHERLAND, STEVEN M.

Patent Trial and Appeal Board (PTAB) Decisions

Total PTAB Decisions
1
Examiner Affirmed
0
(0.0%)
Examiner Reversed
1
(100.0%)
Reversal Percentile
99.0%
Higher than average

What This Means

With a 100.0% reversal rate, the PTAB has reversed the examiner's rejections more often than affirming them. This reversal rate is in the top 25% across the USPTO, indicating that appeals are more successful here than in most other areas.

Strategic Value of Filing an Appeal

Total Appeal Filings
7
Allowed After Appeal Filing
3
(42.9%)
Not Allowed After Appeal Filing
4
(57.1%)
Filing Benefit Percentile
71.6%
Higher than average

Understanding Appeal Filing Strategy

Filing a Notice of Appeal can sometimes lead to allowance even before the appeal is fully briefed or decided by the PTAB. This occurs when the examiner or their supervisor reconsiders the rejection during the mandatory appeal conference (MPEP § 1207.01) after the appeal is filed.

In this dataset, 42.9% of applications that filed an appeal were subsequently allowed. This appeal filing benefit rate is above the USPTO average, suggesting that filing an appeal can be an effective strategy for prompting reconsideration.

Strategic Recommendations

Appeals to PTAB show good success rates. If you have a strong case on the merits, consider fully prosecuting the appeal to a Board decision.

Filing a Notice of Appeal is strategically valuable. The act of filing often prompts favorable reconsideration during the mandatory appeal conference.

Examiner SUTHERLAND, STEVEN M - Prosecution Strategy Guide

Executive Summary

Examiner SUTHERLAND, STEVEN M works in Art Unit 3752 and has examined 134 patent applications in our dataset. With an allowance rate of 100.0%, this examiner allows applications at a higher rate than most examiners at the USPTO. Applications typically reach final disposition in approximately 40 months.

Allowance Patterns

Examiner SUTHERLAND, STEVEN M's allowance rate of 100.0% places them in the 100% percentile among all USPTO examiners. This examiner is more likely to allow applications than most examiners at the USPTO.

Office Action Patterns

On average, applications examined by SUTHERLAND, STEVEN M receive 1.88 office actions before reaching final disposition. This places the examiner in the 45% percentile for office actions issued. This examiner issues fewer office actions than average, which may indicate efficient prosecution or a more lenient examination style.

Prosecution Timeline

The median time to disposition (half-life) for applications examined by SUTHERLAND, STEVEN M is 40 months. This places the examiner in the 25% percentile for prosecution speed. Applications take longer to reach final disposition with this examiner compared to most others.

Interview Effectiveness

Conducting an examiner interview provides a +0.0% benefit to allowance rate for applications examined by SUTHERLAND, STEVEN M. This interview benefit is in the 17% percentile among all examiners. Note: Interviews show limited statistical benefit with this examiner compared to others, though they may still be valuable for clarifying issues.

Request for Continued Examination (RCE) Effectiveness

When applicants file an RCE with this examiner, 33.0% of applications are subsequently allowed. This success rate is in the 71% percentile among all examiners. Strategic Insight: RCEs show above-average effectiveness with this examiner. Consider whether your amendments or new arguments are strong enough to warrant an RCE versus filing a continuation.

After-Final Amendment Practice

This examiner enters after-final amendments leading to allowance in 48.2% of cases where such amendments are filed. This entry rate is in the 73% percentile among all examiners. Strategic Recommendation: This examiner shows above-average receptiveness to after-final amendments. If your amendments clearly overcome the rejections and do not raise new issues, consider filing after-final amendments before resorting to an RCE.

Appeal Withdrawal and Reconsideration

This examiner withdraws rejections or reopens prosecution in 87.5% of appeals filed. This is in the 81% percentile among all examiners. Strategic Insight: This examiner frequently reconsiders rejections during the appeal process compared to other examiners. Per MPEP § 1207.01, all appeals must go through a mandatory appeal conference. Filing a Notice of Appeal may prompt favorable reconsideration even before you file an Appeal Brief.

Petition Practice

When applicants file petitions regarding this examiner's actions, 13.3% are granted (fully or in part). This grant rate is in the 8% percentile among all examiners. Strategic Note: Petitions are rarely granted regarding this examiner's actions compared to other examiners. Ensure you have a strong procedural basis before filing a petition, as the Technology Center Director typically upholds this examiner's decisions.

Examiner Cooperation and Flexibility

Examiner's Amendments: This examiner makes examiner's amendments in 2.2% of allowed cases (in the 76% percentile). Per MPEP § 1302.04, examiner's amendments are used to place applications in condition for allowance when only minor changes are needed. This examiner frequently uses this tool compared to other examiners, indicating a cooperative approach to getting applications allowed. Strategic Insight: If you are close to allowance but minor claim amendments are needed, this examiner may be willing to make an examiner's amendment rather than requiring another round of prosecution.

Quayle Actions: This examiner issues Ex Parte Quayle actions in 1.5% of allowed cases (in the 65% percentile). This examiner issues Quayle actions more often than average when claims are allowable but formal matters remain (MPEP § 714.14).

Prosecution Strategy Recommendations

Based on the statistical analysis of this examiner's prosecution patterns, here are tailored strategic recommendations:

  • Appeal filing as negotiation tool: This examiner frequently reconsiders rejections during the appeal process. Filing a Notice of Appeal may prompt favorable reconsideration during the mandatory appeal conference.
  • Plan for extended prosecution: Applications take longer than average with this examiner. Factor this into your continuation strategy and client communications.
  • Examiner cooperation: This examiner frequently makes examiner's amendments to place applications in condition for allowance. If you are close to allowance, the examiner may help finalize the claims.

Relevant MPEP Sections for Prosecution Strategy

  • MPEP § 713.10: Examiner interviews - available before Notice of Allowance or transfer to PTAB
  • MPEP § 714.12: After-final amendments - may be entered "under justifiable circumstances"
  • MPEP § 1002.02(c): Petitionable matters to Technology Center Director
  • MPEP § 1004: Actions requiring primary examiner signature (allowances, final rejections, examiner's answers)
  • MPEP § 1207.01: Appeal conferences - mandatory for all appeals
  • MPEP § 1214.07: Reopening prosecution after appeal

Important Disclaimer

Not Legal Advice: The information provided in this report is for informational purposes only and does not constitute legal advice. You should consult with a qualified patent attorney or agent for advice specific to your situation.

No Guarantees: We do not provide any guarantees as to the accuracy, completeness, or timeliness of the statistics presented above. Patent prosecution statistics are derived from publicly available USPTO data and are subject to data quality limitations, processing errors, and changes in USPTO practices over time.

Limitation of Liability: Under no circumstances will IronCrow AI be liable for any outcome, decision, or action resulting from your reliance on the statistics, analysis, or recommendations presented in this report. Past prosecution patterns do not guarantee future results.

Use at Your Own Risk: While we strive to provide accurate and useful prosecution statistics, you should independently verify any information that is material to your prosecution strategy and use your professional judgment in all patent prosecution matters.